ÌìÃÀ´«Ã½

Are you a resident or business in the local area? Join our mailing lists

Trams to Newhaven - Highlights from 2022

Aerial photo of Picardy Place with part of the tram stop and the playhouse showing

As we approach the end of 2022, we look back at some of this year's highlights for the Trams to Newhaven project.

Newhaven to Melrose Drive 
•    Last track cross over installed
•    Completion of welfare building 
•    Melrose Drive substation energised

Ocean Terminal to Rennie’s Isle 
•    Completion of works on Victoria Bridge 


Rennie’s Isle to Tower Place
•    In July SFN completed the largest concrete pour to date on the project, which was on the deck of Tower Bridge. This was a dual pour of 82 metres, with two concrete pumps which equates to 164 linear metres of single-track slab having been.  . 

•    In October SFN exceeded this with a concrete pour totalling 170m, this is the longest track pour the project undertook and meant that there was track installed from Picardy Place to Newhaven.

Constitution place to Baltic Street
•    For Robert Burns day in January, Leith’s iconic Burns statue was returned to its home on Bernard Street. .
•    In February the Leith Dock pillars were reinstated

Leith Walk 
•    In July-two way running traffic was introduced between London Road and Pilrig Street. .
•   The new substation at the bottom of Leith Walk was energised. 

London Road to Picardy 
•    In February the decommissioning and removal of the temporary tram stop at York Place began. This enabled the track to be extended along to Picardy Place where the new tram stop has been constructed.
•    The historic London Road clock returned home after 15 years in storage following its full restoration.  .

The Trams to Newhaven project remains on schedule to be operational by Spring 2023. 

December 2021/2022 comparison stats

 

 

Christmas Shutdown Plan
The project will shut down from 5pm on 23 December 2022 and return on  Monday 9 January 2023 to review all safety measures ahead of recommencing main construction activities on Wednesday 11 January 2022. However, system infrastructure works will commence from Wednesday 4 January 2022. 

We would like to thank businesses and residents across the route for their continued patience during the construction of the Trams to Newhaven Project.

Have a merry Christmas and a happy New Year!

 

Published: 23rd December 2022